July 6 Sidewalk Framing & Kitchen Progress
ByEmAreWow, I see that the sidewalk has been framed out as I walk up to the house today. We’ll actually be able to walk from the front porch to the driveway now. Wait! What’s this? The front door is open. It’s inviting me in. ACK! The kitchen cabinets are sitting in place. YES! The master…
June 27 Stuff Is Arriving
ByEmAreIts really cool to see things start to arrive. Not only are the walls getting their initial coats of joint compound, but the garage is full of cabinets, HVAC parts, trim, you name it. We will ignore the flooding around the house for now. Enjoy, and if you are so inclined, check out the full…
June 4 – OMG. We have walls.
ByEm AreOMG. We have walls.
June 28 Rains Bring Mudslide
ByEmAreRain, rain, go away. Come back when the grading is all completed. The rains DID come and created lots of wash-outs, large and small, all around the property. UGH. Not a pretty picture. Enjoy, and if you are so inclined, check out the full set of pics I grabbed today using this link to Amazon…
May 23 – Foundation Gets A Coat
ByEm AreThe foundation received its waterproofing coating today. This will keep all that nasty rainwater out of our basement. Fingers crossed.
May 25 – Grading Taking Shape
ByEm AreSaturday May 25, Memorial Day weekend, shows a lot of progress. The entire rough grading and back-fill of the property appears to have been completed.